โ ๏ธ Preliminary Estimate: All costs are indicative ranges based on estimated total weight of 2,000 MT. Final firm fixed-price quotation will be issued within 5 working days upon receipt of detailed cargo list, dimensions, weights, and drawings.
Inland haulage โ Ex-works from turbine manufacturer's factory in China to designated loading port.
Port operations โ Loading, lashing, securing, and ocean/vessel booking at Chinese port.
International sea freight โ China main port to Bandar Abbas (or Chabahar), Iran.
Iran import clearance โ Full customs brokerage, HS code classification, duty/tax estimation, and exemption handling where applicable.
Oversized cargo permits โ Securing all necessary route permits for heavy/oversized transport across Iran.
Route survey โ Preliminary route assessment from discharge port to site, including bridge/road load capacity verification.
Specialized trailers โ Provision of hydraulic modular trailers, low-bed, or extendable flatbeds as required.
Inland delivery โ From Iranian port of entry to Mil Nader project site, including offloading at site (subject to site accessibility).
Cargo insurance โ All-risk / Institute Cargo Clauses (A) + War & Strike risk, coverage at 110% of CIF value.
Real-time tracking โ Weekly position reports + exception alerts throughout the entire chain.
3 Recommended Route & Transit Time
๐ญ
Origin
Factory, China
Turbine manufacturer
๐
3โ5 days
๐ข
Sea Freight
China โ Bandar Abbas
Breakbulk / Container / RO-RO
โด๏ธ
18โ22 days
๐
Destination
Mil Nader Site
Sistan & Baluchestan, Iran
Segment
Mode
Est. Duration
Remarks
Factory โ Shanghai / Tianjin Port
Truck / Barge
3โ5 days
Depending on factory location
China Port โ Bandar Abbas, Iran
Sea (Breakbulk / Container / RO-RO)
18โ22 days
Subject to vessel schedule
Bandar Abbas โ Mil Nader Site
Truck (Oversized Trailers)
7โ10 days
~800 km, permit-dependent
Total Estimated Door-to-Site
~30โ35 days
Subject to vessel schedule & customs
๐ Route Note: Chabahar Port is an alternative entry point offering shorter trucking distance to Mil Nader (~500 km vs. ~800 km from Bandar Abbas), but with less frequent vessel calls. We recommend Bandar Abbas as primary, Chabahar as secondary upon charter feasibility.
4 Indicative Cost Breakdown (USD, excl. VAT)
Preliminary estimate based on total equipment weight of ~2,000 MT, assuming breakbulk / charter vessel arrangement.
Code
Cost Component
Estimate (USD)
Remarks
A
China Inland Haulage
120,000 โ 180,000
Factory โ port, depending on factory location
B
Port Handling & Lashing (China)
80,000 โ 120,000
Stevedoring, securing materials
C
Ocean Freight (China โ Iran)
350,000 โ 500,000
Charter basis, subject to volume & season
D
Iran Customs Clearance
40,000 โ 60,000
Agent fees, documentation, guarantees
E
Oversized Permits & Route Survey
30,000 โ 50,000
Route survey + provincial permit fees
F
Iran Inland Transport (Port โ Site)
200,000 โ 300,000
Special trailers, escort, police escort if required
G
Cargo Insurance (110% CIF, All-Risk + War/Strike)
25,000 โ 40,000
Premium est. at 0.4โ0.6% of cargo value
H
Project Management & Coordination
20,000 โ 30,000
On-site coordination, tracking, documentation
I
Contingency Buffer (~5โ8%)
50,000 โ 80,000
Port delays, route changes, demurrage
GRAND TOTAL INDICATIVE
~915,000 โ 1,360,000
Final cost subject to detailed DWG/weights
Low: $915KMid: ~$1.14MHigh: $1.36M
5 Maximum Handling Capability
๐๏ธ
150 MT
Max Single-Piece Weight
With modular trailer configuration
๐
90m ร 6m ร 5m
Max Single-Piece Dimensions
Suitable for wind blades & tower sections
๐
6โ12 Axle
Hydraulic Modular Trailers
Extendable decks available
6 Project Experience (Selected References)
Project
Scope
Year
[Project A] โ 50 MW Wind Farm, [Country]
Transport of 10 ร 5 MW turbines, factory-to-site
2023
[Project B] โ Power Plant Equipment, [Country]
800 MT oversized transformers, multimodal
2024
[Project C] โ Wind Blade Delivery, [Country]
69m blades, port-to-site with route survey
2025
Full reference list, contact details, and project photos available upon request.
7 Assumptions & Exclusions
Basis: This quotation is based on the estimated total weight of 2,000 MT. Final cost will be adjusted upon receipt of actual packing list, dimensions, and drawings.
Excluded: Iranian VAT/local taxes, import duties (if not exempted), demurrage/detention due to consignee delay, and any sanctions-related legal fees beyond standard compliance.
Vessel type: Breakbulk / container / hybrid to be confirmed after dimensional verification.
Sanctions compliance: We operate under valid OFAC/EU compliance protocols and will require end-user certificate from Iran counterparty.
8 Next Steps
Provide detailed cargo list โ Dimensions, weights, center of gravity, special lifting points.
Confirm factory location โ For accurate China inland haulage cost calculation.
Confirm Iran import license / exemption status โ To expedite customs clearance process.
Upon above, we will issue a firm fixed-price quotation within 5 working days.